Flood restoration works – roads

Major works Other works Restoration overviewMap of works Important information

Responding to high priority road hazards caused by weather eventsOur local road network suffered significant damage following the February 2022 flood. Additional damage from Tropical Cyclone Alfred is currently estimated.

Subscribe to the Tweed Link for further information on Council's road restoration projects.

Don't remove or tamper with traffic lights or road signage – it puts people at risk and it's illegal. Read more.

The very large volumes of emails, letters and calls since the floods are impacting on recovery works. Before you contact us, please review the information on this page and read our weekly flood recovery update, which provides you with the latest news on how the Tweed is recovering and rebuilding following the floods. Read more about your part in roads flood recovery.

As our road crews and contractors undertake the enormous task of fixing our roads, we ask motorists to please:

  • have patience
  • slow down and drive to the conditions
  • understand that some repairs are only temporary until a more permanent fix can be completed
  • be aware of changed traffic conditions.

Major flood restoration works

Last updated on Tuesday 15 April 2025.

Caution 
Church Street - soil anchors and mesh
Soil anchors and mesh installed at Church Street, Murwillumbah ready for shotcrete.

Batter repair works are ongoing below Church Street and are expected to be completed in October 2025. Progress to date is 100 anchors installed out of an estimated total of 660 and 110 m2 of shotcrete has been used out of expected total of 960 m2. Specialised equipment is on site with Church Street restricted to local traffic only and will be closed until July.

Caution Short delay 
Commissioners Creek Road - armour rock
Armour rock being positioned along the creek side on Commissioners Creek Road.

Council has completed all design work and Transport have approved funding for the project.

Contractor RCC Earthworks has been rectifying and reworking impacts on the site caused by Ex- Cyclone Alfred.

Pavement works are expected to commence this week, weather permitting. Contractors are aiming to have the project completed by the end of May.

Caution Closed 

Contractor PAN Civil has commenced work on Kunghur Creek Road carrying out embankment stabilsation with soil nails and tecco mesh.

The road will be closed between 9 am and 3pm, Monday to Friday. Emergency vehicle access measures are in place.

Caution 
Kyogle Road - Mount Burrell - Guardrail
The newly installed guardrail at the flood restoration site on Kyogle Road at Mt Burrell. Linemarking will be carried out when weather permits.

Kyogle Road at Mount Burrell is reaching completion but has been delayed due to the recent wet weather. Work to be completed includes linemarking.

Construction works on Mt Burrell Road continue and the road is closed just south of property number 323 between 9 am and 3 pm daily.

Caution Short delay 
Kyogle Road - Uki to Mount Warning

Contractor AMC is working on a flood restoration site at 911 Kyogle Road, Dum Dum. This site has changed traffic conditions and is operating under traffic light control 24/7. Work is expected to take about 4 months to complete.

Further work on the road near the former fruit store to repair improved drainage and patching of the road surface will commence next week by contractors, Skeen. The road through this site will also be under traffic light control, reduced to one lane. Work is expected to take about 3 weeks to complete, weather permitting.

Mount Warning Road – completed
Work will commence on 16 April on a safety barrier on the river side of the restoration site on Mount Warning Road, weather permitting.

Work has been completed on Mount Warning Road by contractor Civil Mining & Construction Pty Ltd (CMC).

There will be changed traffic conditions on Mount Warning Road with contractors installing a new guard rail. The road will be reduced to single lane with traffic controls in place from 7 am to 5 pm, weather permitting.

Motorists using Mount Warning Road are urged to take care now that traffic has been moved back on the original alignment.

Caution Short delay 
Compaction works are underway on the upslope lane of the Tyalgum Road slip site.
Compaction works are underway on the upslope lane of the Tyalgum Road slip site.
Tyalgum Road - concrete barriers replaced with traffic cones
Preparation continues on the upslope lane at the Tyalgum Road slip site. Traffic lights are still in place and motorists are advised to use caution.
Contractor SEE Civil continues compaction works at the Tyalgum Road extreme slip site.
Contractor SEE Civil continues compaction works at the Tyalgum Road extreme slip site.

Compaction works continue on the Tyalgum Road extreme slip site with contractor SEE Civil finalising subgrade works.

In the past month, the extreme slip site has experienced an average of 48 mm of rain per week which has impacted on work.

The contractors plan to import road base material, weather permitting, to continue with preparation of the road works.

Stormwater features have been installed and have been put to the test and are working well with drainage.

The concrete barriers have been removed from the centre line of the works and with traffic cones now place. Motorists are advised to use caution through the site and obey the traffic light controls and reduced speed limit.

A SEE Civil spokesperson thanked the community for abiding by the reduced speed limit and showing caution through the work site, especially during the inclement weather.

The expected completion date for permanent works is around May 2025.

Motorists are asked to please keep to the 40 kmph speed limit on the temporary access roadway and to be mindful of local wildlife. Any injured wildlife reports can be phoned through to 02 6672 4789.

Caution 
Byrrill Creek Road and bridge design works - May 2024
Byrrill Creek Road and bridge design has progressed well with the project recently approved for funding by TfNSW. Tenders will take place in early 2025 with works expected to take place in March.

The detailed design for this major project has been finalised and Transport for NSW (TfNSW) have recently approved funding for the project. The works have been tendered and currently being awarded.

Construction start date is being confirmed but aiming for the coming months. Works are expected to take approximately 3 months, and closures of the road are expected between 9 am and 3 pm.

Byrrill Creek Road and bridge design has progressed well with the project recently approved for funding by TfNSW. Planning is underway to place a temporary seal on the gravel approaches in coming weeks.

Caution 
Everinghams Road

Design work for the restoration of a land slips have been completed by Civil Consult and 3 of the 5 projects are currently out to market for the construction tender which closes early March.

Council has received funding for the work which is programmed to commence in the first half of 2025.

Caution 

Design work for the restoration of a land slip on Tomewin Road have been completed by Civil Consult and the project is currently out for tender to the construction market which closes early March.


Council has received funding for the restoration of a land slip site on Tomewin Road and is awaiting final design approval for the work.

Council has received funding for the work which expected to go before Council for final approval at the May meeting.

The site is currently reduced to 40km/hr with a give way sign for the southbound traffic under a work site traffic management plan.

Due to the restricted site distances and nature of Tomewin Drive it is not a suitable location for traffic lights to be installed. Motorists are reminded to adhere to the give way signage on site and reduced 40kmh speed limits.

Other flood restoration works

Council continues to complete flood restoration works on roads damaged in the 2022 Floods. A total of 3780 items were identified as ‘road damage’ across the Tweed Shire from the February and March 2022 events. 

Additional works

Commissioners Creek, Doon Doon and Midginbil Road Slips: a package for the design of 9 slip sites along Commissioners Creek Road, Doon Doon Road and Midginbil Road has been awarded to consultant WSP. TfNSW recently approved $10 million in funding for these projects. Design works have progressed to 30% completion. Works are expected to take place in mid-2025.

Dulguigan Road: Contractor WSP has completed the IFC design works for the sites and this is currently under review by TfNSW.  Restoration works are currently planned to commence in the first half of 2025.

Kyogle Road (Terragon, Uki and Clarrie Hall Dam): Concept designs have been received from WSP for Clarrie Hall Dam Road and Kyogle Road at Terragon and are waiting for approval from TfNSW.


Reserve Creek Road has had safety measures put in place following damage caused by ex-Tropical Cyclone Alfred. The speed limit has been reduced and there is a 4.5 tonne weight limit.

Everingham, Glengarrie and Fernvale Road: Design work for the restoration of land slips have been completed by Civil Consult and 3 of the 5 projects are currently being reviewed. Council has received funding for the work which is programmed to commence in the first half of 2025.

Reserve Creek Road: Safety measures have been put in place on Reserve Creek Road at Reserve Creek around further damage caused by Ex-Cyclone Alfred.

Water barriers are now in place with give way signs through the single lane section. Speed limits have been reduced to 40 km/h and there is a weight limit on the road of 4.5 tonnes. Motorists are urged to proceed with caution and not move barriers.

Bridges package south west

Consultant GHD has completed designs to 85% for Byrrill Creek Bridge, Byangum Bridge on Kyogle Road over the Tweed River, and a major scour on Deards Bridge at Doon Doon Road.

Consultant Bridge Knowledge has completed design drawings for a causeway replacement with a bridge towards the end of Rowlands Creek Road and a causeway replacement at the end of Doon Doon Road.

A causeway replacement on McConnell’s Road has design well-advanced.

Funding has now been approved for these projects These projects will be released as one tender package in early 2025 with works to commence in March/April 2025.

Ophir Glen Road bridge: The design works for the repair to Ophir Glen Bridge are now complete and betterment funding has been approved for the replacement of the current bridge with a new concrete one.

All completion times are subject to weather permitting.

For further information on Council's post-flood road restoration projects, subscribe to the Tweed Link.

This page is updated weekly.

Tweed road restoration projects – an overview

Council is working on strategies to progress the remainder of road repairs following the 2022 flood event. A total of 3780 items have been identified as road damage across Tweed Shire.

We apologise for any inconvenience and ask for your patience as we work through our roadworks program.

Our road crews and contractors will continue to restore flood damage at the following sections of local roads:

    Map of current and flood recovery works

    This element requires javascript to be enabled.

    Please wait while we load your map...

    Important information

    Visit our Emergency Dashboard for useful links, information and contacts in an emergency.

    Don't tamper with traffic lights – it puts people at risk and it's illegal.

    Thieves stealing batteries from mobile traffic control lights are placing motorists’ lives at risk around the Tweed.

    Even more concerning are those wilfully destroying traffic light units by pushing them over the edge of road embankments.

    Vandalised traffic lights at Limpinwood Road

    The units are there to provide safe traffic passage and any action to move or disable the lights places lives in jeopardy.

    The units are there to provide safe traffic passage and any action to move or disable the lights places lives in jeopardy.

    Similarly road signs advising of closures are placed for a reason – to protect the safety of road users.

    When Council officers have to deal with issues regarding traffic control lights or road signage being repaired, reinstalled or cleaned from graffiti, it takes them away from other duties involved in flood recovery. There is also the additional cost of repairing or replacing them.

    Having to respond to matters not directly involved in road repair and restoration simply delays the process.

    Please do not remove or interfere with traffic control systems or road signage - it is a serious offence and police may be notified and hefty fines could be incurred.

    Don't remove road closure signs or barriers

    We urge residents not to remove road closure signs or barriers – they’re there to keep our community safe.

    Removing or tampering with barriers is a serious offence and could result in someone being hurt or killed. Don’t be that person.

    Flood damage to our road network is extremely significant and there are still many roads closed as crews continue with the clean-up.

    Council crews are working as hard as they can but this work will take months, not weeks, to complete.

    Please be patient.

    Your part in roads flood recovery

    We understand that residents would like regular updates and specific answers to questions about flood recovery works. 

    We have received very large volumes of emails, letters and calls since the floods and our staff are currently working through these while also trying to maintain business as usual services.

    Many of these queries can be answered by referring to this page and our weekly flood recovery update.  Time spent responding to demands and answering questions takes key staff away from dealing with the problem.

    This can also result in delays in responding to customer queries or delays in carrying out crucial repairs – which are both frustrating to customers and staff. 

    We are fully aware of the issues and inconvenience caused by such significant damage to our road network and the need to repair quickly and safely. However post-disaster many of these situations are beyond our control.

    For weekly updates on how the Tweed is recovering and rebuilding, please read our weekly flood recovery update.

    You can also find more information about the progress of repairs on significant landslips on this page – this includes slips at Scenic Drive, Tyalgum Road, Kyogle Road, Reserve Creek Road, Limpinwood Road and Mount Warning Road.

    Thank you for your understanding.

    Check road conditions at Live Traffic

    We're constantly updating Live Traffic as we verify road conditions.

    Please note that information is not real-time as issues with access and mobile communication remain, making reliable hazard information hard to confirm.

    We restore access to isolated communities first

    Following severe weather events like floods and bushfires, we prioritise life-threatening situations and worst hit areas. We target our busiest roads and any areas were people are isolated.

    This means that access will not always be restored to normal road standards.

    Learn more about how we build, upgrade and maintain a safe and connected local road network, including how we prioritise road maintenance projects.

    Avoid unnecessary travel

    We ask motorists to avoid all unnecessary travel.

    If you must travel, read our fact sheet(PDF, 288KB) for some tips to help keep you safe on our roads.

    Expect water, fallen trees and possible landslips on the road – on any and every road.