17 October 2016
Council will close Elanora Avenue, between Boronia Avenue and Seabrae Court, Pottsville, for a week from Wednesday 19 October to allow the completion of drainage works.
Residents will be allowed access under the direction of stop / slow flagmen.
During the closure, Council will install drainage pits along Elanora Avenue to allow surface waters to escape the low-lying area more quickly during rains.
The upgrade began in June and works completed to date include:
“The latest discovery of fibre optic cables put the job on hold for two weeks while our design team resolved the conflict, during which time the crews were redeployed to reduce the cost of the delay.”
All works are expected to be completed in about four weeks’ time.