Current planned works
Flood restoration - roads Upcoming planned works Map of works
Stay up to date with what's happening on our roads, follow us on Facebook or visit Live Traffic NSW.
To learn more about how we build, upgrade and maintain a safe and connected local road network, including how we prioritise road maintenance projects, visit our roads page.
Information on this page is intended as a guide. Start and end dates are estimates only and may change for various reasons including weather conditions.
Last updated on Tuesday 17 December 2024.
As part of our commitment to deliver a safe and connected local road network, we'll soon be upgrading the Leisure Drive, Greenway Drive and Darlington Drive intersection in Banora Point.
This project will be delivered in 2 stages (see work zones map below).
Stage 1, located at sites 2, 1 and 5 on the map below, was completed in February 2024. This stage included relocating services (such as gas, telecommunications and water), realigning kerbs and gutters, widening the road and modifying underground drainage.
Stage 2 of the upgrade will be carried out during the Christmas school holidays of 2024/2025, ensuring that the majority of works are completed with minimal disruption to school activities. This stage includes installing a signalised pedestrian crossing and widening lanes to make travel through this area safer and easier for everyone.
For the safety of our crews and the adverse impact on infrastructure quality, works are not able to be undertaken during wet conditions.
Council crews will undertake the works from Monday to Friday, between 7 am and 5 pm. Works may need to be conducted some Saturdays, between 7 am to 1 pm. Linemarking will be carried out at night towards the end of the project.
What to expect during construction:
- There will be no access to the grassed area, about 50 metres east of the roundabout, during construction.
- Two-way traffic will be maintained during construction however, lanes will be narrower and the speed limit will be reduced to 40 km/h.
- Temporary road and lane closures during work hours, which may cause delays of up to 5 minutes.
- Avoid on-road parking during work hours.
- Use alternative routes where possible or allow additional time for your journey.
- During temporary footpath closures, we'll provide clear directions for pedestrians to navigate around the work areas. For pedestrian detours, see work zone maps below.
- The bus stop, west of Advocate Place, will be temporarily relocated about 100 metres to the east, just past Advocate Place.
- Limited access to some properties and driveways within the work zone during work hours. Please ask the traffic controller for help if you need access.Changed traffic conditions with traffic controllers guiding traffic flow during work hours.
- As part of the road widening, drainage improvements and new footpath installation, some trees within the work zone will need to be removed, while others will be saved where possible. In some cases, root systems may be impacted, making preservation unfeasible. Trees that cannot be saved will be replaced with new plantings to maintain the area’s greenery. Additionally, tree trimming will be conducted east of Advocate Place.
For more information visit yoursaytweed.com.au/banora-point-intersection.
Stormwater drainage upgrade to install larger storm water pipes and storm water pits.
Uki and Tweed hinterland residents and regular users of Kyogle Road have been making the most of the road now that the 3 main restoration sites have fully reopened to the public.
Kyogle Road Site B, completed with linemarking and guard rails.
At Kyogle site C, contractor CMC has completed 2 sections which were impacted by the 2022 floods.
At Kyogle Road site A, the road has reopened to dual lane traffic. A speed restriction of 80km/h is in place.
Official completion of CMC’s works on all 3 sites on Kyogle Road and also Mount Warning Road was marked at a media event last week. This marks a significant step forward in the Tweed flood restoration program.
Contractor CMC would like to thank the community for their patience and understanding while the flood restoration works were carried out on this complex project.
Road resealing from Byangum Bridge to Tyalgum Road intersection.
Lane closures will cause traffic delays. Also, the rest area north of Byangum Bridge will be closed during the resealing works, as it will be used as a stockpile area.
On narrower back roads, we typically spray the full width in one pass, which may cause delays of up to 15 minutes.
Safety is our priority – please do not drive or walk on the road while work is underway without approval from onsite crews.
Resealing roads before they deteriorate will help to ensure they remain in good working order for years to come. This saves public money by avoiding the cost and disruption of major reconstruction work if left too long.
Find out more about why we reseal roads.
The detailed design for this major project has been finalised and Transport have recently approved funding for the project.
Tender submissions are currently being reviewed.
Works are expected to commence in early 2025, will take approximately 3 months, and closures of the road are expected between 9 am and 3 pm.
Reconstruction of timber footbridges along the coastal shared footpath between Harper Court and Chatfield Court Park.
Detors will be in place while the timber footbridges are demolished and reconstructed.
Private works. Old Bogangar Bridge will be down to one lane, under traffic control, between 10 am and 2:30 pm. Some nightworks required.
Kingscoast developer is constructing a subdivision near Tweed Coast Road.
Roadworks are underway at Crescent Street. Both lanes are open to traffic with the speed limit reduced to 40 km/h.
If you have any queries, contact the onsite manager Braeden Alexanderson on 0457 457 800.
Road resealing will take place from Melalueca Station south to the end of the divided road near Cudgen Road intersection.
Lane closures may cause minor traffic delays.
On narrower back roads, we typically spray the full width in one pass, which may cause delays of up to 15 minutes.
Safety is our priority – please do not drive or walk on the road while work is underway without approval from onsite crews.
Resealing roads before they deteriorate will help to ensure they remain in good working order for years to come. This saves public money by avoiding the cost and disruption of major reconstruction work if left too long.
Find out more about why we reseal roads.
Road resealing will take place from Cudgen Road intersection north to Melalueca Station.
Lane closures may cause minor traffic delays.
On narrower back roads, we typically spray the full width in one pass, which may cause delays of up to 15 minutes.
Safety is our priority – please do not drive or walk on the road while work is underway without approval from onsite crews.
Resealing roads before they deteriorate will help to ensure they remain in good working order for years to come. This saves public money by avoiding the cost and disruption of major reconstruction work if left too long.
Find out more about why we reseal roads.
Road resealing will take place along Tweed Valley Way between Cane Road and Clothiers Creek Road.
Lane closures may cause traffic delays of up to 10 minutes.
On narrower back roads, we typically spray the full width in one pass, which may cause delays of up to 15 minutes.
Safety is our priority – please do not drive or walk on the road while work is underway without approval from onsite crews.
Resealing roads before they deteriorate will help to ensure they remain in good working order for years to come. This saves public money by avoiding the cost and disruption of major reconstruction work if left too long.
Find out more about why we reseal roads.
Road resealing will take place along Cane Road heading north to past the Clothiers Creek Road turnoff.
Lane closures may cause minor traffic delays.
On narrower back roads, we typically spray the full width in one pass, which may cause delays of up to 15 minutes.
Safety is our priority – please do not drive or walk on the road while work is underway without approval from onsite crews.
Resealing roads before they deteriorate will help to ensure they remain in good working order for years to come. This saves public money by avoiding the cost and disruption of major reconstruction work if left too long.
Find out more about why we reseal roads.
Road resealing will take place from Numinbah Road along Araluen Place.
Lane closures may cause minor traffic delays.
On narrower back roads, we typically spray the full width in one pass, which may cause delays of up to 15 minutes.
Safety is our priority – please do not drive or walk on the road while work is underway without approval from onsite crews.
Resealing roads before they deteriorate will help to ensure they remain in good working order for years to come. This saves public money by avoiding the cost and disruption of major reconstruction work if left too long.
Find out more about why we reseal roads.
Private works. As part of the Tweed Valley Hospital Project, FKG Group is constructing the new Kingscliff ambulance station at the Cudgen Road/Turnock Street/McPhail Avenue roundabout.
As part of the Tweed Valley Hospital project, Lendlease is undertaking private works.
Construction of control building for sewer pump station with access from Bowen Lane. Work will pause over Christmas period.
Flood recovery works. Test borehole drilling complete. Waiting for geo technical report.
Flood recovery works. Test borehole drilling completed. Waiting for geo technical report.
Flood recovery works.
Borehole drilling works are now completed. Awaiting geotechnical report.
Flood recovery works. Test drilling completed. Awaiting geotechnical results.
Flood recovery works.
Borehole drilling works are now completed. Awaiting geotechnical report.
Road resealing will take place between Loders Road and Andersons Road.
Lane closures may cause minor traffic delays.
On narrower back roads, we typically spray the full width in one pass, which may cause delays of up to 15 minutes.
Safety is our priority – please do not drive or walk on the road while work is underway without approval from onsite crews.
Resealing roads before they deteriorate will help to ensure they remain in good working order for years to come. This saves public money by avoiding the cost and disruption of major reconstruction work if left too long.
Find out more about why we reseal roads.
Murwillumbah Cycle Club hosts fortnightly road races for cyclists. Two road racing courses, Eungella (Tyalgum Road) and Dulguigan (Dulguigan Road, Boyds Lane and Urliup Road, are used alternatively. Details at facebook.com/MurbahCycleClub.
Flood recovery works. Test borehole drilling complete. Awaiting geotechnical report.
Heavy road patching on Tweed Valley way at the Minnows Road intersection. Work hours are from 7am to 4pm. The road will be down to one lane during work hours with occasional traffic stoppages up to 5 minutes.
Kings Forest contractors will be closing part of the northbound lane on Tweed Coast Road between 10 am and 2.30pm on Tuesday 14 January for shoulder widening works.
For any queries email Simone Pulefale, Community Liaison Officer.
Footpath installation connecting Marine Parade to Pearl Street via Kingscliff Street.
Flood recovery works. Test borehole drilling complete. Awaiting geotechnical report.
Flood recovery works. Test drilling has been completed. Awaiting test results.
Kyogle Road at Mount Burrell is reaching completion but has been delayed due to the recent wet weather. Work to be completed includes linemarking.
Construction works on Mt Burrell Road continue and the road is closed just south of property number 323 between 9am and 3pm daily.
Kunghur Road will commence in early 2025.
The newly installed guardrail at the flood restoration site on Kyogle Road at Mt Burrell. Linemarking will be carried out when weather permits.
Flood recovery works. Borehole drilling works completed. Awaiting geotechnical report.
Nightworks to install high-friction surface. Temporary lane and road closures, 7 pm to 4 am. Use William Street to access Hardwood Street.
- Harwood Street will be temporarily closed at the Byangum Road intersection during work hours and detours will be in place.
- Byangum Road, at the Harwood Street intersection, will be down to one lane.
- Temporary road closures during work hours, which may cause delays of up to 5 minutes.
- Temporary lane closures for the duration of the works, which may cause delays of up to 10 minutes.
- Please do not use on-street parking within the work zone during work hours.
- Limited access to some properties and driveways within the work zone during work hours. Please ask the traffic controller for help if you need access.
- Changed traffic conditions with traffic controllers guiding traffic flow during work hours.
- Pedestrian movement may be directed or restricted.
The batter repair below Church Street has been awarded to PCA Ground Engineering Pty Ltd at the December 2024 Council meeting. Construction has commenced and is expected to take approximately 8–9 months to complete.
Construction of a new stormwater pump station behind the flood protection levee near Brothers Leagues Club.
Throughout the project, the levee wall and dirt track behind the Brothers Leagues Club football fields will not be accessible to the public.
Sometimes, we'll use the park gate at the end of Murwillumbah Street to transport equipment such as excavators, pipes and trucks to the construction site.
Murwillumbah Street will be used as a temporary haulage route for bringing material in and out of the construction site.
Drainage upgrade works to Frangela Drive Reserve. Most of the works will be completed within the reserve area, except for the upgrade of gully pits. While the gully pits are being upgraded, there will be traffic control in place. Please follow all safety signs and directions from traffic controllers. There will be no pedestrian access through the work site and any pedestrian access into the reserve via Kendon Avenue will be directed.
Roadworks and water and sewer rising main upgrades. See work zone map below.
Hall Drive, Kendon Avenue, Linden Court and Bagoo Avenue will be directly affected by the works. Frances Street, Joshua Street and Sorrell Court may also be impacted.
Temporary lane closures during work hours, which may cause delays of up to 5 minutes. Use alternative routes where possible or allow additional time for your journey.
There will be limited access to some properties and driveways within the work zone during work hours and possibly for one night. Please ask the traffic controller for help if you need access.
Short interruptions to the water supply may be required. These will be detailed in a separate notice.
Work hours are from Monday to Friday, 7 am to 5 pm. To minimise traffic impacts, some work may occasionally be conducted on weekends.
Estimated start dates for each section are as follows:
Water main works:
- Hall Drive (Byangum end) – July
- Hall Drive and Linden Court – August
- Kendon Avenue – September
Sewer main works:
- Near Tweed Valley Adventist College – August
- Near Rous River Way – September
- Near Frances Street – October
Road rehabilitation works along William Street between Thompson Street and Byangum Road. Road closed weekdays 7 am to 5 pm and some Saturdays 7 am to 1 pm. Local access only outside of work hours via Byangum Road with road closure at Thompson Street end.
Road patching works. Expect minor delays
Contractor RCC Civil will commence drainage works, pavement improvement and kerb and guttering on Numinbah Road near the Queensland/NSW border from Monday 17 February 2025 for about 8 weeks weather permitting.
Temporary road closures during work hours, which may cause delays of up to 10 minutes. Traffic control measures will be in place.
Road resealing between Centennial Drive bridge and the cul-de-sac. Lane closures may cause minor traffic delays.
Lane closures may cause minor traffic delays.
On narrower back roads, we typically spray the full width in one pass, which may cause delays of up to 15 minutes.
Safety is our priority – please do not drive or walk on the road while work is underway without approval from onsite crews.
Resealing roads before they deteriorate will help to ensure they remain in good working order for years to come. This saves public money by avoiding the cost and disruption of major reconstruction work if left too long.
Find out more about why we reseal roads.
85% of designs have been developed and are being reviewed by Transport for NSW.
Work on site is expected to start early this year.
Sewer pump station upgrade work will occur weekdays from 7 am to 5 pm, with possible Saturday work from 7 am to 1 pm. Expect temporary lane closures at Tweed Valley Way and Buchanan Street during work hours, causing delays of up to 10 minutes. Traffic controllers will be on site to assist. Access to some properties and driveways within the work zone will be limited, ask a traffic controller if you need access. Pedestrians will be detoured to use the footpath on the opposite side of the road.
Water main upgrade between Quarry Road and Wuffs Lane. Temporary lane closures may cause brief delays.
Work hours are from Monday to Friday, between 7 am and 5 pm.
- Short interruptions to the water supply may be required.
- Limited access to some properties and driveways within the work zone during work hours. Please ask the traffic controller for help if you need access.
- Temporary lane closures during work hours, which may cause delays of up to 5 minutes.
- No pedestrian access through the work site.
Private works. Road reduced to one lane for the duration of the project. Reconstruction road, drainage, kerb and gutter, footpath and school crossing works.
Road patching between between Rayles Lane and the Tweed River. Lane closures may cause minor traffic delays.
On narrower back roads, we typically spray the full width in one pass, which may cause delays of up to 15 minutes.
Safety is our priority – please do not drive or walk on the road while work is underway without approval from onsite crews.
Find out more about why we reseal roads.
Design work for the restoration of a land slip on Tomewin Road has been completed by Civil Consult and is now waiting on completion of the Environmental approvals.
Council has received funding for the restoration of a land slip site on Tomewin Road and is awaiting final design approval for the work.
Council has received funding for the work which is programmed to commence in the first quarter of 2025.
The site is currently reduced to 40km/hr with a give way sign for the southbound traffic under a work site traffic management plan.
Private works. Changed traffic conditions during the construction of the new southern entry road.
SEE Civil, on behalf of the Gold Coast Airport, is building the new southern entry road, connecting the Gold Coast Highway at the NSW/QLD border to the Gold Coast Airport.
If you have any questions or concerns, please contact SEE Civil directly:
For more details, refer to the September 2024 update. To receive project updates, send your name, address and email to:
As part of our Footpath Rehabilitation Program, we'll be upgrading the footpath along Wharf Street, between Bay Street and the entrance to Tweed Mall.
Work hours will be from Monday to Friday, 7 am to 5 pm. Works may need to be conducted some Saturdays, between 7 am to 1 pm.
There may be lane closures and lane narrowing, which may cause brief traffic delays. Traffic controllers will be in place to direct traffic during work hours.
Pedestrians will be redirected around the work site. No pedestrian access will be allowed through the construction area.
Water main upgrade along Enterprise Avenue (north of Traders Way) and Traders Way.
Work hours are Monday to Friday, 7 am to 5 pm.
Temporary lane closures may cause delays of up to 5 minutes.
There will be limited access to some properties and driveways within the work zone during work hours. Please ask the traffic controller for help if you need access.
Sewer rising main upgrade.
Council crews will be carrying out the works from Monday to Friday, between 7 am and 5 pm.
Changed traffic conditions with traffic controllers guiding traffic flow during work hours.
There will be limited access to some properties and driveways within the work zone during work hours. Please ask the traffic controller for help if you need access.
Water main upgrade along Minjungbal Drive from Kirkwood Road to Tweed City.
To minimise disruptions, works are scheduled to start after the NSW school holidays and will take about 5 weeks to complete, weather permitting.
Work hours are from Monday to Friday, 7 am to 5 pm. Works may need to be conducted some Saturdays, between 7 am and 1 pm.
-
Temporary lane closures along Minjungbal Drive and Kirkwood Road during work hours, which may cause delays of up to 10 minutes.
-
The Blundell Boulevard entrance to Tweed City will be closed for trenching work across the entrance (see schedules below, weather permitting). Please use the Kirkwood Road or Machinery Drive entrances instead. The Blundell Boulevard entrance will be open outside of work hours. Please follow all safety signs and message boards for guidance.
Friday 29 November:
Full entrance closure from 3 pm, reopening around 10 pm.
Monday 2 December:
Partial entrance closure from 7 am, reopening around 4 pm.
Tuesday 3 to Thursday 5 December:
Partial entrance closure from 7 am, reopening around 4 pm.
-
There will be no pedestrian access through the worksite, on the eastern footpath along Minjungbal Drive, for the duration of the works. Pedestrians will be directed to use the footpath on the western side of the road.
-
One westbound lane on Kirkwood Road, at the approach to Minjungbal Drive intersection, was closed while workers installed the main along that section of the roadway.
-
The southbound left-turn lane into Tweed City at Blundell Boulevard was closed while crews installed the main along that section of the roadway. Motorists were asked to use the alternate entrances at Kirkwood Road or Machinery Drive.
Contractor SEE Civil has achieved a significant milestone in the flood restoration work at the extreme slip site on Tyalgum Road.
The Tyalgum Road flood restoration has reached a major milestone with the completion of piling operations. The piling rig and heavy lift crane are being removed from the site along with other heavy equipment.
Contractors have completed the piling operations, a major milestone in the restoration of the Tyalgum Road slip site.
Tweed Shire Council, Rix piling contractors and SEE Civil crew mark the completion of piling operations on the Tyalgum Road slip site.
The site, one of the most complex in the Tweed, currently involves drilling and installing 66 concrete piles on the upslope side of the site and this was achieved on the weekend.
Piling contractor RIX has completed constructing a total of 130 piles on the sites to secure the slip area having commenced the work in March, 2024. RIX completed 64 piles for the bottom row of the slip site before transferring operations to the upslope side of the site in September 2024.
Contractors are now progressing in core drilling through the concrete piles and tie-back works are due to commence this week.
In other significant works, heavy equipment is being demobilised from the site.
With the completion of piling, traffic will remain under traffic light control while work continues and a SEE Civil spokesperson said the community had been abiding by the reduced speed limit.
The expected completion date for permanent works remains mid-2025.
Motorists are asked to please keep to the 40 km/h speed limit on the temporary access roadway and to be mindful of local wildlife. Any injured wildlife reports can be phoned through to 02 6672 4789.
Road resealing will take place from Tyalgum Creek Road to Stoddarts Road creek causeway.
Lane closures may cause minor traffic delays.
On narrower back roads, we typically spray the full width in one pass, which may cause delays of up to 15 minutes.
Safety is our priority – please do not drive or walk on the road while work is underway without approval from onsite crews.
Resealing roads before they deteriorate will help to ensure they remain in good working order for years to come. This saves public money by avoiding the cost and disruption of major reconstruction work if left too long.
Find out more about why we reseal roads.
Flood recovery works. Borehole drilling works completed.
Road resealing will take place from culvert on Tyalgum Creek Road west of Stoddarts Road to just west of Eaglehawk Close.
Lane closures may cause minor traffic delays.
On narrower back roads, we typically spray the full width in one pass, which may cause delays of up to 15 minutes.
Safety is our priority – please do not drive or walk on the road while work is underway without approval from onsite crews.
Resealing roads before they deteriorate will help to ensure they remain in good working order for years to come. This saves public money by avoiding the cost and disruption of major reconstruction work if left too long.
Find out more about why we reseal roads.
Works will commence on the three slips along Tumbulgum Road by contractor Skeen Constructions from 3 February for 8 weeks, weather permitting.
Temporary road closures during work hours, which may cause delays of up to 10 minutes. Traffic control measures will be in place for the duration of the works and residents are asked to take care through the work sites.
Design works are nearing completion. The construction tender responses for these packages have been received.
The tender outcome was presented to Council in December with Australian Marine and Civil Pty Ltd being awarded the works package.
Planned commencement is early February 2025.
Direct communications with impacted residents on the Wollumbin side of the bridge will be undertaken in the coming weeks regarding the need to close the bridge to vehicular traffic for 2-3 days in April.
Flood recovery works.
Borehole drilling works completed. Awaiting geotechnical report.
Flood recovery works 80% complete. Gabion basket repairs to be undertaken.
Road patching between the Hogans Road causeway and Majestic Court. Lane closures may cause minor traffic delays.
Lane closures may cause minor traffic delays.
On narrower back roads, we typically spray the full width in one pass, which may cause delays of up to 15 minutes.
Safety is our priority – please do not drive or walk on the road while work is underway without approval from onsite crews.
Find out more about why we reseal roads.
Map of current and flood restoration works
This element requires javascript to be enabled.Please wait while we load your map...