Current planned works
Flood restoration - roads Upcoming planned works Map of works
Stay up to date with what's happening on our roads, follow us on Facebook or visit Live Traffic NSW.
To learn more about how we build, upgrade and maintain a safe and connected local road network, including how we prioritise road maintenance projects, visit our roads page.
Information on this page is intended as a guide. Start and end dates are estimates only and may change for various reasons including weather conditions.
Last updated on Tuesday 17 December 2024.
The bus stop along Darlington Drive, near the intersection of Banora Hills Drive, will be relocated about 60 metres south.
The bus stop relocation is designed to improve safety and efficiency for buses making turns. This change will enhance the safety and functionality of our local road network for passengers, drivers and residents.
Work hours are Monday to Friday, 7 am to 3 pm.
Please do not use on-street parking during work hours.
The road will remain open however an exclusion zone will be established using traffic cones or witches’ hats. Please follow the signage.
Pedestrian movement may be directed or restricted.
As part of our commitment to deliver a safe and connected local road network, we'll soon be upgrading the Leisure Drive, Greenway Drive and Darlington Drive intersection in Banora Point.
This project will be delivered in 2 stages (see work zones map below).
Stage 1, located at sites 2, 1 and 5 on the map below, was completed in February 2024. This stage included relocating services (such as gas, telecommunications and water), realigning kerbs and gutters, widening the road and modifying underground drainage.
Stage 2 of the upgrade will be carried out during the Christmas school holidays of 2024/2025, ensuring that the majority of works are completed with minimal disruption to school activities. This stage includes installing a signalised pedestrian crossing and widening lanes to make travel through this area safer and easier for everyone.
For the safety of our crews and the adverse impact on infrastructure quality, works are not able to be undertaken during wet conditions.
Council crews will undertake the works from Monday to Friday, between 7 am and 5 pm. Works may need to be conducted some Saturdays, between 7 am to 1 pm. Linemarking will be carried out at night towards the end of the project.
What to expect during construction:
- There will be no access to the grassed area, about 50 metres east of the roundabout, during construction.
- Two-way traffic will be maintained during construction however, lanes will be narrower and the speed limit will be reduced to 40 km/h.
- Temporary road and lane closures during work hours, which may cause delays of up to 5 minutes.
- Avoid on-road parking during work hours.
- Use alternative routes where possible or allow additional time for your journey.
- During temporary footpath closures, we'll provide clear directions for pedestrians to navigate around the work areas. For pedestrian detours, see work zone maps below.
- The bus stop, west of Advocate Place, will be temporarily relocated about 100 metres to the east, just past Advocate Place.
- Limited access to some properties and driveways within the work zone during work hours. Please ask the traffic controller for help if you need access.Changed traffic conditions with traffic controllers guiding traffic flow during work hours.
- As part of the road widening, drainage improvements and new footpath installation, some trees within the work zone will need to be removed, while others will be saved where possible. In some cases, root systems may be impacted, making preservation unfeasible. Trees that cannot be saved will be replaced with new plantings to maintain the area’s greenery. Additionally, tree trimming will be conducted east of Advocate Place.
For more information visit yoursaytweed.com.au/banora-point-intersection.
Stormwater drainage upgrade to install larger storm water pipes and storm water pits.
Uki and Tweed hinterland residents and regular users of Kyogle Road have received an early Christmas present with contractor Civil Mining & Construction Pty Ltd (CMC) completing works on 3 major slip sites on the road.
Kyogle Road site B has been fully restored and open to dual lanes of traffic.
Kyogle Road site C has been fully restored and open to dual lanes of traffic.
Kyogle Road site C has been fully restored and open to dual lanes of traffic.
Final finishing works have been carried out at sites B and C with the removal; of traffic lights at all 3 major sites. Normal traffic conditions have been restored. Contractor CMC would like to thank the community for their patience and understanding while the flood restoration works were carried out on this complex project.
Electronic roadworks signage will provide up-to-date information.
The detailed design for this major project has been finalised, and Transport have recently approved funding for the project.
Tender submissions are currently being reviewed. Works are expected to commence in early 2025 will take approximately 3 months, and closures of the road are expected between 9 am and 3 pm.
Byrrill Creek Road and bridge design has progressed well with the project recently approved for funding by TfNSW. Tenders will take place in early 2025 with works expected to take place in March.
Flood recovery works. Test borehole drilling completed. Awaiting geotechnical report.
Reconstruction of timber footbridges along the coastal shared footpath between Harper Court and Chatfield Court Park.
Detors will be in place while the timber footbridges are demolished and reconstructed.
Private works. Old Bogangar Bridge will be down to one lane, under traffic control, between 10 am and 2:30 pm. Some nightworks required.
Kingscoast developer is constructing a subdivision near Tweed Coast Road.
Roadworks are underway at Crescent Street. Both lanes are open to traffic with the speed limit reduced to 40 km/h.
If you have any queries, contact the onsite manager Braeden Alexanderson on 0457 457 800.
Council has completed all design work and Transport have approved funding for the project.
Contractor RCC Earthworks has commenced work and the project is expected to take about 5 months. The work will include 1km of road reconstruction, protection works and a new causeway.
The contractors will be taking a break over the Christmas/New Year period and resuming work in early 2025.
Private works. As part of the Tweed Valley Hospital Project, FKG Group is constructing the new Kingscliff ambulance station at the Cudgen Road/Turnock Street/McPhail Avenue roundabout.
As part of the Tweed Valley Hospital project, Lendlease is undertaking private works.
Construction of control building for sewer pump station with access from Bowen Lane. Work will pause over Christmas period.
Stormwater drain clearing, about 500 metres south of the Cudgen Road intersection, may cause brief traffic delays.
Flood recovery works. Test borehole drilling complete. Waiting for geo technical report.
Flood recovery works. Test borehole drilling completed. Waiting for geo technical report.
Flood recovery works.
Borehole drilling works are now completed. Awaiting geotechnical report.
Flood recovery works. Test drilling completed. Awaiting geotechnical results.
Flood recovery works.
Borehole drilling works are now completed. Awaiting geotechnical report.
Flood restoration works ongoing.
Road resealing will take place between Loders Road and Andersons Road.
Lane closures may cause minor traffic delays.
On narrower back roads, we typically spray the full width in one pass, which may cause delays of up to 15 minutes.
Safety is our priority – please do not drive or walk on the road while work is underway without approval from onsite crews.
Resealing roads before they deteriorate will help to ensure they remain in good working order for years to come. This saves public money by avoiding the cost and disruption of major reconstruction work if left too long.
Find out more about why we reseal roads.
Murwillumbah Cycle Club hosts fortnightly road races for cyclists. Two road racing courses, Eungella (Tyalgum Road) and Dulguigan (Dulguigan Road, Boyds Lane and Urliup Road, are used alternatively. Details at facebook.com/MurbahCycleClub.
Flood recovery works. Test borehole drilling complete. Awaiting geotechnical report.
Road resealing will take place between Barlee Drive and Boston Place.
Lane closures may cause minor traffic delays.
On narrower back roads, we typically spray the full width in one pass, which may cause delays of up to 15 minutes.
Safety is our priority – please do not drive or walk on the road while work is underway without approval from onsite crews.
Resealing roads before they deteriorate will help to ensure they remain in good working order for years to come. This saves public money by avoiding the cost and disruption of major reconstruction work if left too long.
Find out more about why we reseal roads.
Heavy road patching on Tweed Valley way at the Minnows Road intersection. Work hours are from 7am to 4pm. The road will be down to one lane during work hours with occasional traffic stoppages up to 5 minutes.
Kings Forest developers have started work on the installation of a temporary koala fencing, sediment and erosion control and service location.
These works are the precursor to major roadworks commencing, which will include the provision of a roundabout, road and surfacing improvements, lighting, drainage, fauna underpasses and service installation.
For any queries email Simone Pulefale, Community Liaison Officer.
Private works - connection of residence to sewer main.
Flood recovery works. Test borehole drilling complete. Awaiting geotechnical report.
Flood recovery works. Test drilling has been completed. Awaiting test results.
Kyogle Road at Mount Burrell is reaching completion but has been delayed due to the recent wet weather. Work to be completed includes linemarking.
The newly installed guardrail at the flood restoration site on Kyogle Road at Mt Burrell. Linemarking will be carried out when weather permits.
Construction works on Mt Burrell Road continue and the road is closed just south of property number 323. between 9am and 3pm daily. In case of emergency, please call Kade Gray on 0422 938 823.
Work will continue up till Christmas with work to cease over the holiday period.
Kunghur Road will commence in early 2025.
Flood recovery works. Borehole drilling works completed. Awaiting geotechnical report.
Work has been completed on Mount Warning Road by contractor Civil Mining & Construction Pty Ltd (CMC).
Mt Warning Road has been fully restored following the devastating floods of 2022.
Motorists using the Mt Warning Road are urged to take care now that traffic has been moved back on the original alignment.
Road patching mid-way along Mount Warning Road - work ongoing.
The batter repair below Church Street has just been approved by TfNSW and the construction tender responses have been received and are being presented to the December 2024 Council meeting.
Construction is expected to commence in early-mid January 2024 taking approximately 6 months to complete.
Construction of a new stormwater pump station behind the flood protection levee near Brothers Leagues Club.
Throughout the project, the levee wall and dirt track behind the Brothers Leagues Club football fields will not be accessible to the public.
Sometimes, we'll use the park gate at the end of Murwillumbah Street to transport equipment such as excavators, pipes and trucks to the construction site.
Murwillumbah Street will be used as a temporary haulage route for bringing material in and out of the construction site.
Roadworks and water and sewer rising main upgrades. See work zone map below.
Hall Drive, Kendon Avenue, Linden Court and Bagoo Avenue will be directly affected by the works. Frances Street, Joshua Street and Sorrell Court may also be impacted.
Temporary lane closures during work hours, which may cause delays of up to 5 minutes. Use alternative routes where possible or allow additional time for your journey.
There will be limited access to some properties and driveways within the work zone during work hours and possibly for one night. Please ask the traffic controller for help if you need access.
Short interruptions to the water supply may be required. These will be detailed in a separate notice.
Work hours are from Monday to Friday, 7 am to 5 pm. To minimise traffic impacts, some work may occasionally be conducted on weekends.
Estimated start dates for each section are as follows:
Water main works:
- Hall Drive (Byangum end) – July
- Hall Drive and Linden Court – August
- Kendon Avenue – September
Sewer main works:
- Near Tweed Valley Adventist College – August
- Near Rous River Way – September
- Near Frances Street – October
Private works. Lane closure. Businesses in this area will have restricted access under traffic control.
Road resealing between Centennial Drive bridge and the cul-de-sac. Lane closures may cause minor traffic delays.
Lane closures may cause minor traffic delays.
On narrower back roads, we typically spray the full width in one pass, which may cause delays of up to 15 minutes.
Safety is our priority – please do not drive or walk on the road while work is underway without approval from onsite crews.
Resealing roads before they deteriorate will help to ensure they remain in good working order for years to come. This saves public money by avoiding the cost and disruption of major reconstruction work if left too long.
Find out more about why we reseal roads.
85% of designs have been developed and are being reviewed by Transport for NSW.
Work on site is expected to start early next year.
Sewer pump station upgrade work will occur weekdays from 7 am to 5 pm, with possible Saturday work from 7 am to 1 pm. Expect temporary lane closures at Tweed Valley Way and Buchanan Street during work hours, causing delays of up to 10 minutes. Traffic controllers will be on site to assist. Access to some properties and driveways within the work zone will be limited, ask a traffic controller if you need access. Pedestrians will be detoured to use the footpath on the opposite side of the road.
Private works. Road reduced to one lane for the duration of the project. Reconstruction road, drainage, kerb and gutter, footpath and school crossing works.
Road patching between between Rayles Lane and the Tweed River. Lane closures may cause minor traffic delays.
On narrower back roads, we typically spray the full width in one pass, which may cause delays of up to 15 minutes.
Safety is our priority – please do not drive or walk on the road while work is underway without approval from onsite crews.
Find out more about why we reseal roads.
Asphalt replacement on Terranora Road, at the intersection of The Parapet, is scheduled to take about 3 weeks, weather permitting.
Due to high traffic volumes and limited detour options, the work will be done as nightworks, from Sunday to Thursday, between 6 pm and 4:30 am.
Expect temporary road closures during work hours, with possible delays of up to 15 minutes.
Design work for the restoration of a land slip on Tomewin Road has been completed by Civil Consult and is now waiting on completion of the Environmental approvals.
Council has received funding for the restoration of a land slip site on Tomewin Road and is awaiting final design approval for the work.
Council has received funding for the work which is programmed to commence in the first quarter of 2025. The site is currently reduced to 40km/hr with a give way sign for the southbound traffic under a work site traffic management plan.
Due to the restricted site distances and nature of Tomewin Drive it is not a suitable location for traffic lights to be installed. Motorists are reminded to adhere to the give way signage on site and reduced 40km/hr speed limits.
Private works. Changed traffic conditions during the construction of the new southern entry road.
SEE Civil, on behalf of the Gold Coast Airport, is building the new southern entry road, connecting the Gold Coast Highway at the NSW/QLD border to the Gold Coast Airport.
If you have any questions or concerns, please contact SEE Civil directly:
For more details, refer to the September 2024 update. To receive project updates, send your name, address and email to:
Sewer rising main upgrade.
Council crews will be carrying out the works from Monday to Friday, between 7 am and 5 pm.
Changed traffic conditions with traffic controllers guiding traffic flow during work hours.
There will be limited access to some properties and driveways within the work zone during work hours. Please ask the traffic controller for help if you need access.
Water main upgrade along Minjungbal Drive from Kirkwood Road to Tweed City.
To minimise disruptions, works are scheduled to start after the NSW school holidays and will take about 5 weeks to complete, weather permitting.
Work hours are from Monday to Friday, 7 am to 5 pm. Works may need to be conducted some Saturdays, between 7 am and 1 pm.
-
Temporary lane closures along Minjungbal Drive and Kirkwood Road during work hours, which may cause delays of up to 10 minutes.
-
The Blundell Boulevard entrance to Tweed City will be closed for trenching work across the entrance (see schedules below, weather permitting). Please use the Kirkwood Road or Machinery Drive entrances instead. The Blundell Boulevard entrance will be open outside of work hours. Please follow all safety signs and message boards for guidance.
Friday 29 November:
Full entrance closure from 3 pm, reopening around 10 pm.
Monday 2 December:
Partial entrance closure from 7 am, reopening around 4 pm.
Tuesday 3 to Thursday 5 December:
Partial entrance closure from 7 am, reopening around 4 pm.
-
There will be no pedestrian access through the worksite, on the eastern footpath along Minjungbal Drive, for the duration of the works. Pedestrians will be directed to use the footpath on the western side of the road.
-
One westbound lane on Kirkwood Road, at the approach to Minjungbal Drive intersection, was closed while workers installed the main along that section of the roadway.
-
The southbound left-turn lane into Tweed City at Blundell Boulevard was closed while crews installed the main along that section of the roadway. Motorists were asked to use the alternate entrances at Kirkwood Road or Machinery Drive.
The bus stop along Jacaranda Avenue, north of Red Bass Avenue, will be relocated about 90 metres north.
The bus stop relocation is designed to improve safety and efficiency for buses making turns. This change will enhance the safety and functionality of our local road network for passengers, drivers and residents.
Work hours are Monday to Friday, 7 am to 3 pm.
Please do not use on-street parking during work hours.
The road will remain open however an exclusion zone will be established using traffic cones or witches’ hats. Please follow the signage.
Pedestrian movement may be directed or restricted.
As the year draws to an end, contractor SEE Civil continues to make solid progress with flood restoration work on Tyalgum Road.
The piling rig and heavy lift crane are working their way along the upslope of the Tyalgum Road extreme slip, drilling and inserting concrete piles.
Council’s Fergus McDonald and SEE Civil’s Greg Irvine inspect a casing that has been lowered 12m down into bedrock at Tyalgum Road slip site.
An aerial view of work on the SEE Civil site on Tyalgum Road slip.
Work on the extreme slip site, one of the most complex in the Tweed, currently involves drilling and installing 66 concrete piles on the upslope side of the site.
Piling contractor RIX has completed 45 piles to date, marking more than 66% of the total pilling work completed.
Traffic will remain under traffic light control while work continues and a SEE Civil spokesperson said the vast majority of motorists are abiding by the reduced speed limit, especially since monitoring cameras had been installed.
Work crews will be taking a break over Christmas but the site will continue to be monitored by SEE Civil staff.
The expected completion date for permanent works remains mid-2025.
Access through the slip site remains open to all vehicles under traffic lights. Please note the 40 km/h speed limit along the access road.
Motorists are asked to please keep to the 40 km/h speed limit on the temporary access roadway and to be mindful of local wildlife.
Any injured wildlife reports can be phoned through to 02 6672 4789.
Road resealing will take place from Tyalgum Creek Road to Stoddarts Road creek causeway.
Lane closures may cause minor traffic delays.
On narrower back roads, we typically spray the full width in one pass, which may cause delays of up to 15 minutes.
Safety is our priority – please do not drive or walk on the road while work is underway without approval from onsite crews.
Resealing roads before they deteriorate will help to ensure they remain in good working order for years to come. This saves public money by avoiding the cost and disruption of major reconstruction work if left too long.
Find out more about why we reseal roads.
Flood recovery works. Borehole drilling works completed.
Road resealing will take place from culvert on Tyalgum Creek Road west of Stoddarts Road to just west of Eaglehawk Close.
Lane closures may cause minor traffic delays.
On narrower back roads, we typically spray the full width in one pass, which may cause delays of up to 15 minutes.
Safety is our priority – please do not drive or walk on the road while work is underway without approval from onsite crews.
Resealing roads before they deteriorate will help to ensure they remain in good working order for years to come. This saves public money by avoiding the cost and disruption of major reconstruction work if left too long.
Find out more about why we reseal roads.
Design works are nearing completion. The construction tender responses for these packages have been received.
The tender outcome is being presented to Council in December with the planned commencement in January 2025 pending approvals.
Road resealing will take place from Norco Street to the end of the road seal on Milsoms Lane.
Lane closures may cause minor traffic delays.
On narrower back roads, we typically spray the full width in one pass, which may cause delays of up to 15 minutes.
Safety is our priority – please do not drive or walk on the road while work is underway without approval from onsite crews.
Resealing roads before they deteriorate will help to ensure they remain in good working order for years to come. This saves public money by avoiding the cost and disruption of major reconstruction work if left too long.
Find out more about why we reseal roads.
Flood recovery works.
Borehole drilling works completed. Awaiting geotechnical report.
Flood recovery works 80% complete. Gabion basket repairs to be undertaken.
Road patching between the Hogans Road causeway and Majestic Court. Lane closures may cause minor traffic delays.
Lane closures may cause minor traffic delays.
On narrower back roads, we typically spray the full width in one pass, which may cause delays of up to 15 minutes.
Safety is our priority – please do not drive or walk on the road while work is underway without approval from onsite crews.
Find out more about why we reseal roads.
Map of current and flood restoration works
This element requires javascript to be enabled.Please wait while we load your map...