Current planned works
Tropical Cyclone Alfred has caused some damage to the road network and crews are working to survey, assess and complete the required repairs.
Flood restoration - roads Upcoming planned works Map of works
Stay up to date with what's happening on our roads, follow us on Facebook or visit Live Traffic NSW.
To learn more about how we build, upgrade and maintain a safe and connected local road network, including how we prioritise road maintenance projects, visit our roads page.
Information on this page is intended as a guide. Start and end dates are estimates only and may change for various reasons including weather conditions.
Last updated on Wednesday 7 May 2025.
For asphalt rejuvenation works, Admiralty Place, Midship Court, Seafarer Place and Bosun Boulevard in Banora Point will be temporarily closed during work hours.
What to expect:
- Work hours will be Monday to Friday 7 am to 5 pm, and possibly Saturday 7 am and 1 pm.
- Please do not use on-street parking during work hours.
- Limited access to some properties and driveways within the work zone during work hours. Please ask the traffic controller for help if you need access.
- Use alternative routes where possible.
Linemarking will be completed at the end of the project. Weather permitting.
For asphalt rejuvenation works, Alpha Way, Narara Crescent, Kimberly Circuit and Winders Place in Banora Point will be temporarily closed during work hours.
What to expect:
- Work hours will be Monday to Friday 7 am to 5 pm, and possibly Saturday 7 am and 1 pm.
- Please do not use on-street parking during work hours.
- Limited access to some properties and driveways within the work zone during work hours. Please ask the traffic controller for help if you need access.
- Use alternative routes where possible.
Linemarking will be completed at the end of the project. Weather permitting.
As part of our commitment to delivering a safe and connected local road network, we are upgrading the Leisure Drive, Greenway Drive and Darlington Drive intersection in Banora Point.
This project is being delivered in 2 stages – see work zones map below:
- Stage 1, located at sites 2, 1, and 5 on the map below, was completed in February 2024. This stage included relocating services (such as gas, telecommunications, and water), realigning kerbs and gutters, widening the road, and modifying underground drainage.
- Stage 2, located at sites 3 and 4 pm the map below, will include the installation of a signalised pedestrian crossing, kerb and gutter works, stormwater drainage modifications and pavement widening
The road, drainage, kerb, verge, footpath, bus stop, and light pole relocation works have been completed.
Crews finished the sealing works in late February, and since then, the project has been temporarily on hold while we await approval from Transport for NSW to proceed with the construction of the traffic signals. During this period, there has been minimal disruption to the community, with traffic continuing to flow freely in both directions.
Once approval is received, crews will begin trenching, signal installation, and final concrete works. Additionally, adjustments to pram ramps at the Leisure Drive roundabout and installation of pedestrian fencing will take place. Final asphalt works and line marking will be conducted at night. The remaining works are expected to take about 9 weeks to complete.


For more information visit yoursaytweed.com.au/banora-point-intersection.
For asphalt rejuvenation works, Oatlands Place, Riverlands Place, Ashlar Place, Concord Street and Riversdale Boulevarde in Banora Point will be temporarily closed during work hours.
What to expect:
- Work hours will be Monday to Friday 7 am to 5 pm, and possibly Saturday 7 am and 1 pm.
- Please do not use on-street parking during work hours.
- Limited access to some properties and driveways within the work zone during work hours. Please ask the traffic controller for help if you need access.
- Use alternative routes where possible.
Linemarking will be completed at the end of the project. Weather permitting.
For asphalt rejuvenation works, Owenia Circuit, Snowgum Drive, Aspen Place, Lake Tahoe Drive and Mount Bilinga Circuit in Bilambil Heights will be temporarily closed during work hours.
What to expect:
- Work hours will be Monday to Friday 7 am to 5 pm, and possibly Saturday 7 am and 1 pm.
- Please do not use on-street parking during work hours.
- Limited access to some properties and driveways within the work zone during work hours. Please ask the traffic controller for help if you need access.
- Use alternative routes where possible.
Linemarking will be completed at the end of the project. Weather permitting.
Road resealing between Second Avenue and Greenvale Court.
Lane closures may cause minor traffic delays.
On narrower back roads, we typically spray the full width in one pass, which may cause delays of up to 15 minutes.
Safety is our priority – please do not drive or walk on the road while work is underway without approval from onsite crews.
Find out more about why we reseal roads.
Road resealing of either side of the first rail trail crossing on Burringbar Road heading west.
Lane closures may cause minor traffic delays.
On narrower back roads, we typically spray the full width in one pass, which may cause delays of up to 15 minutes.
Safety is our priority – please do not drive or walk on the road while work is underway without approval from onsite crews.
Find out more about why we reseal roads.
Road resealing at the intersection of Tyalgum Road and Kyogle Road.
Lane closures may cause minor traffic delays.
On narrower back roads, we typically spray the full width in one pass, which may cause delays of up to 15 minutes.
Safety is our priority – please do not drive or walk on the road while work is underway without approval from onsite crews.
Find out more about why we reseal roads.
Uki and Tweed hinterland residents and regular users of Kyogle Road have been making the most of the road now that the 3 main restoration sites have fully reopened to the public.
Kyogle Road Site B, completed with linemarking and guard rails.
At Kyogle site C, contractor CMC has completed 2 sections which were impacted by the 2022 floods.
At Kyogle Road site A, the road has reopened to dual lane traffic. A speed restriction of 80km/h is in place.
Official completion of CMC’s works on all 3 sites on Kyogle Road and also Mount Warning Road was marked at a media event last week. This marks a significant step forward in the Tweed flood restoration program.
Contractor CMC would like to thank the community for their patience and understanding while the flood restoration works were carried out on this complex project.
Road resealing from Byangum Bridge to Tyalgum Road intersection.
Lane closures will cause traffic delays. Also, the rest area north of Byangum Bridge will be closed during the resealing works, as it will be used as a stockpile area.
On narrower back roads, we typically spray the full width in one pass, which may cause delays of up to 15 minutes.
Safety is our priority – please do not drive or walk on the road while work is underway without approval from onsite crews.
Resealing roads before they deteriorate will help to ensure they remain in good working order for years to come. This saves public money by avoiding the cost and disruption of major reconstruction work if left too long.
Find out more about why we reseal roads.
Flood recovery works. Work commenced Monday 5 May 2025. Stabilisation of downslope embankment involving drilling, soil nailing and shotcreting. Traffic controllers operating, expect minor delays.
For asphalt rejuvenation works, Nautilus Way (between Windsong Way and Oasis Way), Edgewater Lane, Oasis Way and Castaway Lane in Casuarina will be temporarily closed during work hours.
What to expect:
- Work hours will be Monday to Friday 7 am to 5 pm, possibly Saturday between 7 am and 1 pm.
- Please do not use on-street parking during work hours.
- Limited access to some properties and driveways within the work zone during work hours. Please ask the traffic controller for help if you need access.
- Use alternative routes where possible.
Linemarking will be completed at the end of the project. Weather permitting.
Kingscoast developer is constructing a subdivision near Tweed Coast Road.
Roadworks are underway at Crescent Street. Both lanes are open to traffic with the speed limit reduced to 40 km/h.
If you have any queries, contact the onsite manager Braeden Alexanderson on 0457 457 800.
For asphalt rejuvenation works, Rutile Street, Terrace Street and Walsh Street in Chinderah will be temporarily closed during work hours.
What to expect:
- Work hours will be Monday to Friday 7 am to 5 pm, and possibly Saturday 7 am and 1 pm.
- Please do not use on-street parking during work hours.
- Limited access to some properties and driveways within the work zone during work hours. Please ask the traffic controller for help if you need access.
- Use alternative routes where possible.
Linemarking will be completed at the end of the project. Weather permitting.
Road resealing will take place along Tweed Valley Way, between Melaleuca Station and the Cudgen Road intersection.
Traffic interruptions:
Lane closures may cause delays of up to 15 minutes. All traffic will be directed into one lane, in each direction, throughout the bitumen sealing works. Please use alternative routes where possible. Consider using Terranora Road and Clothiers Creek Road as alternatives.
Work hours:
Work will be done on weekdays from 7 am to 5 pm. Some weekend work (7 am to 5 pm) and nightworks (6 pm to 6 am) may be needed to reduce traffic interruptions. Weather permitting, the bitumen sealing works are expected to be completed in 3 days, followed by sweeping, linemarking and other related work over the next 2 to 3 weeks.
Safety first:
For your safety, please do not drive or walk on the road while work is underway, unless approved by onsite crews.
Why we’re doing this:
Resealing roads before they deteriorate will help to ensure they remain in good working order for years to come. This saves public money by avoiding the cost and disruption of major reconstruction work if left too long. Find out more about why we reseal roads.
Armour rock being positioned along the creek side on Commissioners Creek Road.
Council has completed all design work and Transport have approved funding for the project.
Contractor RCC Earthworks has been rectifying and reworking impacts on the site caused by Ex-Tropical Cyclone Alfred.
Pavement works are underway, weather permitting. Seal was placed on site last week. The project is currently sitting at 80% and scheduled to be completed by the end of May.
Road resealing will take place along Cane Road heading north to past the Clothiers Creek Road turnoff.
Lane closures may cause minor traffic delays.
On narrower back roads, we typically spray the full width in one pass, which may cause delays of up to 15 minutes.
Safety is our priority – please do not drive or walk on the road while work is underway without approval from onsite crews.
Resealing roads before they deteriorate will help to ensure they remain in good working order for years to come. This saves public money by avoiding the cost and disruption of major reconstruction work if left too long.
Find out more about why we reseal roads.
Private works. As part of the Tweed Valley Hospital Project, FKG Group is constructing the new Kingscliff ambulance station at the Cudgen Road/Turnock Street/McPhail Avenue roundabout.
As part of the Tweed Valley Hospital project, Lendlease is undertaking private works.
Flood recovery works. Test borehole drilling complete. Waiting for geo technical report.
Flood recovery works. Test borehole drilling completed. Waiting for geo technical report.
Flood recovery works.
Borehole drilling works are now completed. Awaiting geotechnical report.
Flood recovery works. Test drilling completed. Awaiting geotechnical results.
Flood recovery works.
Borehole drilling works are now completed. Awaiting geotechnical report.
Murwillumbah Cycle Club hosts fortnightly road races for cyclists. Two road racing courses, Eungella (Tyalgum Road) and Dulguigan (Dulguigan Road, Boyds Lane and Urliup Road, are used alternatively. Details at facebook.com/MurbahCycleClub.
Flood recovery works. Test borehole drilling complete. Awaiting geotechnical report.
Kings Forest developers will be carrying out asphalt works on Tweed Coast Road near the Depot Road Intersection. The closure will occur between 10 am and 2:30 pm from Monday 28 April to Friday, 9 May 2025. Expect minor delays.
For any queries email Simone Pulefale, Community Liaison Officer.
For asphalt rejuvenation works, Bellbird Drive, Drift Court, Spoonbill Lane, Channel Place, Dove Close, Kingfisher Circuit and Pitta Court in Kingscliff will be temporarily closed during work hours.
What to expect:
- Work hours will be Monday to Friday 7 am to 5 pm, and possibly Saturday 7 am and 1 pm.
- Please do not use on-street parking during work hours.
- Limited access to some properties and driveways within the work zone during work hours. Please ask the traffic controller for help if you need access.
- Use alternative routes where possible.
Linemarking will be completed at the end of the project. Weather permitting.
Asphalt replacement on Pearl Street between Kingscliff Street and Turnock Street from Monday, 14 April for 2 days. Work hours from 6:30 am to 4:30 pm. Temporary road closures and detours during work hours, which may cause delays of up to 5 minutes.
Flood recovery works. Test borehole drilling complete. Awaiting geotechnical report.
Flood recovery works. Test drilling has been completed. Awaiting test results.
Flood recovery works. Borehole drilling works completed. Awaiting geotechnical report.
Contractors spray shotcrete onto the bank at Church Street, Murwillumbah.
Batter repair works are ongoing below Church Street and are expected to be completed in October 2025.
Progress to date is 200 anchors installed out of an estimated total of 660 and 175m2 of shotcrete has been used out of expected total of 960m2.
Specialised equipment is on site with Church Street restricted to local traffic only and will be closed until July.
As part of our Footpath Rehabilitation Program, we'll be upgrading the footpath along Commercial Road, between Hartigan Street and Elizabeth Lane.
Work hours will be from Monday to Friday, 7 am to 5 pm. Works may need to be conducted some Saturdays, between 7 am to 1 pm.
-
Access routes will remain the same except when crews are working on James Street. During those times, there will be no entry to James Street from Commercial Road.
-
There may be lane closures and lane narrowing, which may cause brief traffic delays. Traffic controllers will be in place to direct traffic during work hours.
-
On street parking will be unavailable in the work areas. The work will be done in sections, so not all parking areas will be blocked at once. Please avoid parking near barricaded areas during work hours.
-
Pedestrian access through the work site will not be permitted. However, the work will be completed in sections and only the section being worked on will be barricaded.
Phase 1 of the project will involve removing and replacing tree cells, roots and related infrastructure, as well as planting 4 new street trees in Murwillumbah and Brisbane Streets, Murwillumbah. Work hours are 7am to 5pm. Expect minor delays.
The installation of water service lines on Warana Avenue and Tree Street.
This will involve traffic control with short delays between 7:30 am to 5 pm Monday to Friday.
As part of our Footpath Rehabilitation Program, we'll be upgrading the footpath along Wollumbin Street, between Brisbane Street and Factory Lane.
Work hours will be from Monday to Friday, 7 am to 5 pm and possibly some Saturdays, between 7 am to 1 pm.
- Access to some shopfronts may be temporarily restricted. We’ll do our best to maintain access and if your business will be affected, our project team will contact you directly.
- There may be lane closures and lane narrowing, which could result in traffic delays of up to 2 minutes. Traffic controllers will be in place to direct traffic during work hours.
- Some car parks will be unavailable in the work areas. The work will be done in sections, so not all car parks will be blocked at once. Please avoid parking near barricaded areas during work hours.
- Pedestrian access through the work site will not be permitted. However, the work will be completed in sections and only the section being worked on will be barricaded.
- Some public parking bays near the KFC area will be used as laydown areas during construction.
- Some trees within the work zone may need to be trimmed.
For asphalt rejuvenation works, Kellehers Road in Pottsville, between and Overall Drive and Tallon Court will be temporarily closed during work hours.
What to expect:
- Work hours will be Monday to Friday 7 am to 5 pm, and possibly Saturday 7 am and 1 pm.
- Please do not use on-street parking during work hours.
- Limited access to some properties and driveways within the work zone during work hours. Please ask the traffic controller for help if you need access.
- Use alternative routes where possible.
Linemarking will be completed at the end of the project. Weather permitting.
For asphalt rejuvenation works, Tallon Court in Pottsville, at western end to overall Drive will be temporarily closed during work hours.
What to expect:
- Work hours will be Monday to Friday 7 am to 5 pm, and possibly Saturday 7 am to 1 pm.
- Please do not use on-street parking during work hours
- Limited access to some properties and driveways within the work zone during work hours. Please ask the traffic controller for help if you need access.
- Use alternative routes where possible.
Linemarking will be completed at the end of the project. Weather permitting.
Road resealing will take place from Pumpenbil Road for about 400m on Pinnacle Road.
Lane closures may cause minor traffic delays.
On narrower back roads, we typically spray the full width in one pass, which may cause delays of up to 15 minutes.
Safety is our priority – please do not drive or walk on the road while work is underway without approval from onsite crews.
Resealing roads before they deteriorate will help to ensure they remain in good working order for years to come. This saves public money by avoiding the cost and disruption of major reconstruction work if left too long.
Find out more about why we reseal roads.
Road resealing will take place along Pinnacle Road about 3.5km south west of Pumpenbil Road intersection.
Lane closures may cause minor traffic delays.
On narrower back roads, we typically spray the full width in one pass, which may cause delays of up to 15 minutes.
Safety is our priority – please do not drive or walk on the road while work is underway without approval from onsite crews.
Resealing roads before they deteriorate will help to ensure they remain in good working order for years to come. This saves public money by avoiding the cost and disruption of major reconstruction work if left too long.
Find out more about why we reseal roads.
Water main upgrade between Quarry Road and Wuffs Lane. Temporary lane closures may cause brief delays.
Work hours are from Monday to Friday, between 7 am and 5 pm.
- Short interruptions to the water supply may be required.
- Limited access to some properties and driveways within the work zone during work hours. Please ask the traffic controller for help if you need access.
- Temporary lane closures during work hours, which may cause delays of up to 5 minutes.
- No pedestrian access through the work site.
For asphalt rejuvenation works, Dalton Street, Sunnycrest Drive and Nassau Avenue in Terranora will be temporarily closed during work hours.
What to expect:
- Work hours will be Monday to Friday 7 am to 5 pm, possibly Saturday 7 am and 1 pm.
- Please do not use on-street parking during work hours.
- Limited access to some properties and driveways within the work zone during work hours. Please ask the traffic controller for help if you need access.
- Use alternative routes where possible.
Linemarking will be completed at the end of the project. Weather permitting.
For asphalt rejuvenation works, Clipper Court, Navigators Way and Quayside Court in Tweed Heads will be temporarily closed during work hours.
What to expect:
- Work hours will be Monday to Friday 7 am to 5 pm, and possibly Saturday 7 am and 1 pm.
- Please do not use on-street parking during work hours.
- Limited access to some properties and driveways within the work zone during work hours. Please ask the traffic controller for help if you need access.
- Use alternative routes where possible.
Linemarking will be completed at the end of the project. Weather permitting.
Private works. Changed traffic conditions during the construction of the new southern entry road.
SEE Civil, on behalf of the Gold Coast Airport, is building the new southern entry road, connecting the Gold Coast Highway at the NSW/QLD border to the Gold Coast Airport.
If you have any questions or concerns, please contact SEE Civil directly:
For more details, refer to the September 2024 update. To receive project updates, send your name, address and email to:
Water main upgrade along Enterprise Avenue (north of Traders Way) and Traders Way.
Work hours are Monday to Friday, 7 am to 5 pm.
Temporary lane closures may cause delays of up to 5 minutes.
There will be limited access to some properties and driveways within the work zone during work hours. Please ask the traffic controller for help if you need access.
Repair and construction of footpath connecting Prowse Street to Lloyd Street and on to Dry Dock Road.
Water main upgrade along full length of Inlet Drive and Lakes Drive (between Gollan Drive and Inlet Drive).
There will be temporary lane closures which may cause delays of up to 5 minutes.
Work hours are from Monday to Friday, between 7 am and 5 pm.
There may be short interruptions to the water supply. You will be notified separately before this occurs.
There will be limited access to some properties and driveways within the work zone during work hours. Please ask the traffic controller for help if you need access.
There will be no pedestrian access through the work site.
Road patching from Larkins Road intersection north for about 600m.
Lane closures may cause minor traffic delays.
On narrower back roads, we typically spray the full width in one pass, which may cause delays of up to 15 minutes.
Safety is our priority – please do not drive or walk on the road while work is underway without approval from onsite crews.
Find out more about why we reseal roads.
Compaction works continue on the upslope lane of the Tyalgum Road slip site.
Preparation continues on the upslope lane at the Tyalgum Road slip site. Traffic lights are still in place and motorists are advised to use caution.
Work on the Tyalgum Road extreme slip site continues with contractor SEE Civil preparing the site for sealing in the coming weeks.
Work on the site has been hampered by wet weather, making it difficult for the sub-base to dry out.
The contractors are monitoring the weather and condition of the materials on site and are planning for sealing work to commence once weather permits.
As the project nears completion, upcoming works will include sealing of lanes, the installation of a guardrail, turf and hydro mulching and linemarking.
Motorists are advised to use caution through the site and obey the traffic light controls and reduced speed limit.
A SEE Civil spokesperson thanked the community for abiding by the reduced speed limit and showing caution through the work site, especially during the inclement weather.
The expected completion date for permanent works is towards the end of May/early June 2025.
Motorists are asked to please keep to the 40 kmph speed limit on the temporary access roadway and to be mindful of local wildlife. Any injured wildlife reports can be phoned through to 02 6672 4789.
Flood recovery works. Borehole drilling works completed.
Contractor AMC is commencing work on a flood restoration site at 1555 Kyogle Road, Uki.
This site has changed traffic conditions and is operating under traffic light control 24/7. Work is expected to take About 4 weeks to complete. Once this section is complete works are scheduled to commence at 887 Kyogle Rd, Dum Dum.
Mt Warning Bridge
The Mt Warning Bridge deck has been ordered and fabrication is expected by the end of this month and installation in July.
Direct communications with impacted residents on the Wollumbin side of the bridge will be undertaken in the coming weeks regarding the need to close the bridge to vehicular traffic for a minimum of 3 days during restoration.
The design for the approaches is currently being completed by the end of May.
Road resealing will take place on Burringbar Road from Ophir Glen Road to just past rail trail crossing heading east.
Lane closures may cause minor traffic delays.
On narrower back roads, we typically spray the full width in one pass, which may cause delays of up to 15 minutes.
Safety is our priority – please do not drive or walk on the road while work is underway without approval from onsite crews.
Resealing roads before they deteriorate will help to ensure they remain in good working order for years to come. This saves public money by avoiding the cost and disruption of major reconstruction work if left too long.
Find out more about why we reseal roads.
Flood recovery works.
Borehole drilling works completed. Awaiting geotechnical report.
Flood recovery works 80% complete. Gabion basket repairs to be undertaken.
Map of current and flood restoration works
This element requires javascript to be enabled.Please wait while we load your map...